Great Lakes Dredge and Dock Co. has announced that the dredge Ellis Island has returned to Dare County to assist the Liberty Island with the Buxton beach renourishment project.
On Tuesday morning, the Ellis Island resumed dredging operations in Buxton after 10 days of work on the South Nags Head project.
The Ellis Island used the landing point that was previously being used by the Liberty Island, located near the south end of Tower Circle in Buxton, and began pumping north in front of the Outer Banks Motel around 12 p.m. on Tuesday.
Upon the arrival of the Ellis Island, the Liberty Island moved to another submerged pipeline located 3,000 feet north of the northern boundary of Buxton and started pumping south toward the Ellis Island.
Great Lakes Dredge and Dock Co. has placed over 540,000 cubic yards of sand along 4,000 feet of oceanfront. This volume is equivalent to approximately 45 percent of the total project volume. The 1.2 million cubic yard beach renourishment project is expected to be completed by late August.